Redesign or last-time buy? A decision guide with cost comparison

After a discontinuation, there are usually two options: buy once more or redevelop. Which questions drive the decision, how to compare the costs fairly and when a combination of both works best.

Development boards with many colourful cables in front of a keyboardDiscontinuations

Foto: Zan Lazarevic / Unsplash

In brief: Whether a last-time buy or a redesign is more economical is not decided by the component price, but by the total cost over the remaining service life of the product. A last-time buy is usually cheaper if the product only runs for a few more years and demand can be planned. A redesign tends to pay off with a long remaining service life, uncertain demand or when further discontinuations on the same assembly are foreseeable. Often a combination of both is the best solution.

The options at a glance

Last-time buy and redesign are the two ends of a scale. In between there are further options that you should check before deciding.

SolutionTypical effortTime requiredMain risk
Last-time buycapital, storage, testsshort, until the order deadlinewrong quantity, ageing in storage
Replacement component, directly interchangeabletesting and approvalweeks to monthshidden deviations
Authorised aftermarket supplierhigher unit priceshortavailability and price over the years
Purchase on the open marketunit price and test costsshortcounterfeits
Minor redesignadapting circuit or layout, requalificationmonthsfollow-up changes, approval
Major redesignredevelopment of assembly or devicemonths to yearscosts, deadlines, approval

IEC 62402 explicitly names these solutions and requires that the most economical one be selected according to defined criteria. Before deciding between the extremes, it is therefore worth looking for a suitable replacement component. How the search works is described in the article Received a discontinuation notice – what now?.

The questions that drive the decision

How long must the product remain available?

The most important question. With two or three years of remaining service life, almost everything speaks for a last-time buy. With ten or twenty years, the calculation becomes uncertain: the quantity is hard to forecast, storage costs and ageing grow, and further discontinuations are almost certain.

How reliable is demand?

Stable series with known customers are easy to calculate. Fluctuating demand, new customers or unclear maintenance commitments turn any quantity into a bet. Buying too little means an emergency purchase on the open market, buying too much means written-off goods.

What does a change to the product cost?

In regulated industries, even a small redesign can trigger extensive requalification or re-approval. This is often the largest cost block and the longest time factor. Clarify early which evidence a change requires.

Are further discontinuations foreseeable?

If the discontinued component sits on an assembly with other at-risk components, the calculation changes. A redesign can then solve several problems at once, while each last-time buy only postpones one. A current BOM analysis shows the status of the remaining components.

Can the component be stored for a long time?

Not every component survives ten years in storage without loss of quality. Storage methods and tests cost money and belong in the comparison.

Does a redesign bring additional benefits?

A redesign is not only a cost factor. It can improve functions, reduce manufacturing costs, meet new standards or make the product fit for further years. This benefit belongs honestly in the assessment.

Compare costs fairly

The most common mistake is a skewed comparison: on one side only the component price of the last-time buy, on the other the full development bill. Instead, compare the total costs of both options over the same remaining service life.

Last-time buyRedesign
Components for the entire remaining demanddevelopment, layout and software adaptation
Long-term storage and sample testssamples, tests and requalification
Tied-up capitalapproval and customer releases
Insurance, inventory, administrationdocumentation and production adaptation
Risk of shortfall and emergency purchaserisk of delays and follow-up changes
Write-off of leftover goodsremaining stock of old components that is no longer needed

A simplified example

A device must remain available for another ten years. A microcontroller is discontinued, the remaining demand is 2,500 units at 12 euros each. Three further components on the same assembly are classified as at risk.

ItemLast-time buyRedesign
Components for the remaining demand€30,000–
Long-term storage and sample tests over 10 years€15,000–
Tied-up capital, simplified€6,000–
Development and layout–€60,000
Samples, tests and requalification–€40,000
Documentation, production, releases–€15,000
Total for this component€51,000€115,000
Expected costs for the three further components€70,000included in the redesign
Total over the remaining service life€121,000€115,000

Looking only at the microcontroller, the last-time buy is clearly cheaper. Including the foreseeable follow-up discontinuations, both options are almost equal – and the redesign additionally brings ten years of peace on the assembly. The figures are example values. What matters is the principle: calculate over the entire remaining service life and the whole assembly, not over a single component.

How to determine the quantity for the last-time buy is shown in the article Calculating a last-time buy. Which hidden costs a discontinuation also triggers can be read in the article What does obsolescence cost?.

The best solution is often a combination

In practice, the decision is rarely between a pure last-time buy and an immediate redesign. A bridge buy is often the best route: you buy as much as you need until a planned redesign is completed, plus a reserve. This maintains deliverability, reduces tied-up capital and storage risk and gives development time to implement the redesign without pressure.

Even better is to bundle several foreseeable discontinuations in one planned redesign instead of solving each one individually. This only works if the risks of the whole bill of materials are known.

Decision aid at a glance

SituationTendency
Short remaining service life, stable demandlast-time buy
Long remaining service life, uncertain demandredesign or bridge buy plus redesign
High costs for requalification or approvalrather last-time buy or directly interchangeable replacement
Further at-risk components on the assemblyrather redesign, bundle discontinuations
Component poorly suited for storagerather redesign or aftermarket supplier
Redesign brings additional benefitsrather redesign

Document the decision

Record which options were examined, which assumptions the calculation is based on and who decided. This helps with audits and customer questions – and with the next discontinuation. IEC 62402 provides that the criteria for selecting solutions are described in the obsolescence management plan.

Typical mistakes

  • The component price is compared with the full development costs
  • Storage, tied-up capital and tests are missing from the calculation
  • Further at-risk components on the assembly are not considered
  • Costs for requalification and approval are underestimated
  • The decision is made under time pressure shortly before the order deadline
  • A last-time buy is made, but the redesign that is actually needed is never planned

Checklist for the decision

  • Remaining service life and maintenance commitments are clarified
  • The remaining demand is calculated and agreed
  • Replacement components and aftermarket suppliers are checked
  • Further risks on the assembly are known
  • Costs of both options are calculated over the same remaining service life
  • Effort for requalification and approval is assessed
  • A bridge buy has been checked as an option
  • Assumptions, options and decision are documented

Frequently asked questions

When is a last-time buy worthwhile?

Above all when the product is only delivered or maintained for a few more years, demand can be planned and the component can be stored well. High costs for requalification or approval also speak for a last-time buy.

When is a redesign better?

With a long remaining service life, uncertain demand and when further discontinuations on the assembly are foreseeable. A redesign then solves several problems at once and can also improve functions or manufacturing costs.

What is a bridge buy?

A purchase that does not cover the entire remaining demand, but only the period until a planned redesign is completed, plus a reserve. It combines the security of a last-time buy with a permanent solution.

How much time do I have for the decision?

Usually only until the manufacturer's last order date, often a few months after the discontinuation. Demand calculation, cost comparison and approvals take time. Start immediately after receiving the notice – or better before, when the BOM analysis shows a component as at risk.

Note: the calculation example is simplified, all amounts are example values. Solution options and the term life of need buy according to IEC 62402:2019.

Dominik Göttler

About the author

Dominik Göttler

Obsolescence manager · certified according to IEC 62402

Engineer and specialised obsolescence manager with more than 100 discontinuation cases handled in aerospace, medical technology, defence and transport. Publications in Productronic, Markt&Technik and all-electronics.